March reliabilities were published last week, and unortunately this time the numbers are not good for PIC: 86% reliability. It is our worst result since last June and the first time we don't reach the target for Tier-1s since then. Anyhow, we can still try and get a positive view out of it: how much those events that seem "external" to us can affect our site reliability.
The March unreliabilty came mainly from three events: First, the unexpected power cut that affected the whole building in the afternoon of March 13 (don't know the last report about it, but they were talking about somebody pressing the red button without noticing it). Second, there was an outage in the OPN dark fibre between Geneva and Madrid on the 25th that lasted for almost three hours.
The last source of SAM unreliability was of a slightly different nature: the OPS VO disk pools filled up due to massive DTEAM test transfers. So, this last one was under our domain, but actually it did not affect the LHC experiments service, only the monitoring. Anyhow, we have to take and understand SAM for the good and for the bad.
Last month we also had our yearly electrical shutdown during the Easter week. The impact of that scheduled downtime appears in the availability figure, which decreases 12 percentage points down to 74%.
So, it was a tough month in terms of management metrics to be reported (we will see these low points in graphs and tables many times in the following months, that's life). Anyhow, the scheduled intervention went well, and the LHC experiments were not that much affected, so I really believe that our customers are still satisfied. Let's keep them like this.
Thursday, 24 April 2008
Friday, 18 April 2008
Pic farm kicking
Two days ago the new HP blades were deployed at PIC after doing the required current update at the RAC level. The new CPUs are amazingly fast and ATLAS production system is feeding our nodes with a huge amount of jobs which are being devorated by the blades. We reached a peak of more than 500 jobs running in parallel and almost 1000 jobs finished in one day, only taking into account the ATLAS VO.
This is clearly visible in the following figures, impressive ramp-up in walltime and jobs finished per day:


Notice there are some reds in the figures as there were some configuration errors at the very beginnig, quickly resolved by the people maintaining the batch system (new things always bring new issues!).
The contribution of the Spanish sites to ATLAS MonteCarlo production has been throttled, altgough we are far from the gigantic Tier-1s we are firmly growing up and showing robustness (figure below: spanish sites are tagged as "ES" and shown in blue):

We keep seeing the advantage of using the pilot jobs schema as the new nodes were rapidly spotted by this "little investigators" and some hours after the deployment, all the blades were happily fizzing.
This is clearly visible in the following figures, impressive ramp-up in walltime and jobs finished per day:


Notice there are some reds in the figures as there were some configuration errors at the very beginnig, quickly resolved by the people maintaining the batch system (new things always bring new issues!).
The contribution of the Spanish sites to ATLAS MonteCarlo production has been throttled, altgough we are far from the gigantic Tier-1s we are firmly growing up and showing robustness (figure below: spanish sites are tagged as "ES" and shown in blue):

We keep seeing the advantage of using the pilot jobs schema as the new nodes were rapidly spotted by this "little investigators" and some hours after the deployment, all the blades were happily fizzing.
Monday, 14 April 2008
Network bottleneck for the Tier-2s

Last week we reached a new record at PIC: the export transfer rate to the Tier-2 centres. On wednesday the 9th April, around noon, we were transfering data to the Tier-2s at 2Gbps. CMS started very strong on Moday. Pepe was so happy with the resurrected FTS, that started to comission channels to the Tier-2s like hell. Around thursday, CMS lost a bit of steam, but it looks like ATLAS kicked in exporting data to the UAM at a quite serious rate, so the weekly plot ends up quite fancy (attached picture).
The not-so-good news are that actually this 2Gbps is not only a record, but a bottleneck. At CESCA, in Barcelona, the Catalan RREN routes our traffic to RedIRIS (non-OPN sites) through a couple of Gigabit cables. Last October they confirmed us this fact (and now we have measured it ourselves) and also told us that they were planning to migrate this infrastructure to 10Gbps. So far so good. Now let's see if with the coming kick-off of the Spanish Networking Group for WLCG this plan gets to reality.
Monday, 7 April 2008
FTS collapse!
Last week it was the week of the FTS collapse at PIC. Our local FTS instance had been getting slower and slower since quite a while. The cause seemed to be the high load of the oracle backend DB. The Oracle host had a constant load around 30, and we could see that there was a clear bottleneck in the I/O to disk. In the end, three weeks ago, we sort of concluded that the cause of this was that the tables of the FTS DB contained ALL the transfers done since we started the service. One of the main tables had more than 2 million rows! Any SELECT query on it was killing the server with IOPS (I/O requests per second, that was at the level of 600 according to Luis, our DBA). Apparently, an "fts history package" existed since almost one year that did precisely this needed cleanup. However, it seems that it had some problem so it was not really working until a new version was released on mid march this year. Unfortunately, it was too late for us. The history job was archiving old rows too slowly. After starting it, the load of our DB backend did not change at all. We were stuck.
The DDT transfers for CMS were so degraded, that most of the PIC channels had been decomissioned in the last days (see CMS talk). On thursday the 3rd April, we decided to solve this following a radical recipe: restart the FTS with a completely new DB. We lost the history rows, but at least the service was again up and running.
Now, let's try to recomission all those FTS channels asap... and quit the CMS blacklist!
The DDT transfers for CMS were so degraded, that most of the PIC channels had been decomissioned in the last days (see CMS talk). On thursday the 3rd April, we decided to solve this following a radical recipe: restart the FTS with a completely new DB. We lost the history rows, but at least the service was again up and running.
Now, let's try to recomission all those FTS channels asap... and quit the CMS blacklist!
Thursday, 20 March 2008
Easter downtime, and February reliability
We have just had our yearly shutdown. PIC was completely stopped for more than 24 hours... how cool is a silent machine room!
The main intervention was the upgrade of 5 racks to 32A power lines. Now we can plug our HP blade centers. Will see how the PBS behaves when we scale-up the number of Workers by a factor of three.
This week we also got the results for the February reliability from the WLCG office. Our colleagues from Taiwan got the gold medal (100% reliability) breaking CERN's monopoly on this figure. PIC's reliability was very good as well. Actually, we reached our record: 99% reliability. And we got the silver medal for February.
The small 1% that we missed this time to reach the 100% was due to few hours of problems caused by a log file not rotating in the pnfs and a "not enough transparent" intervention in the Info System for dCache, which is still quite patchy for SRMv2.2.
Most probably next month's result will not be so green, due to the unscheduled power cut we had last week and the scheduled yearly shutdown this week. So, let's enjoy our silver medal until the next results come.
The main intervention was the upgrade of 5 racks to 32A power lines. Now we can plug our HP blade centers. Will see how the PBS behaves when we scale-up the number of Workers by a factor of three.
This week we also got the results for the February reliability from the WLCG office. Our colleagues from Taiwan got the gold medal (100% reliability) breaking CERN's monopoly on this figure. PIC's reliability was very good as well. Actually, we reached our record: 99% reliability. And we got the silver medal for February.
The small 1% that we missed this time to reach the 100% was due to few hours of problems caused by a log file not rotating in the pnfs and a "not enough transparent" intervention in the Info System for dCache, which is still quite patchy for SRMv2.2.
Most probably next month's result will not be so green, due to the unscheduled power cut we had last week and the scheduled yearly shutdown this week. So, let's enjoy our silver medal until the next results come.
Friday, 14 March 2008
Power Cut!
Yesterday evening, around 16:30 (luckily we were still around) the lights went off. We still do not have the complete picture, but it seems that somebody by mistake pushed the red button "swith off the building".
The cooling of the machine room stopped, but the machines at PIC still were working powered by the UPS. After 10 min in this situation, we decided to start stopping services. Not much later, the (yet to be understood) glitch arrived. All of the racks lost power for less than 1 second. After this, and to avoid that servers would still restart after a dirty stop, we just switched off all racks in the electric main board.
Today, at 8:00, we started switching on PIC. The good news is that it looks as if we did not have many hardware incidences after the dirty stop. The lesson learnt (hard way) is that we are still too far away from a controlled and efficient complete shutdown. We will have to repeat this on monday, due to the yearly electrical maintenance. So overall, it will be a good week to debug all this procedures.
The cooling of the machine room stopped, but the machines at PIC still were working powered by the UPS. After 10 min in this situation, we decided to start stopping services. Not much later, the (yet to be understood) glitch arrived. All of the racks lost power for less than 1 second. After this, and to avoid that servers would still restart after a dirty stop, we just switched off all racks in the electric main board.
Today, at 8:00, we started switching on PIC. The good news is that it looks as if we did not have many hardware incidences after the dirty stop. The lesson learnt (hard way) is that we are still too far away from a controlled and efficient complete shutdown. We will have to repeat this on monday, due to the yearly electrical maintenance. So overall, it will be a good week to debug all this procedures.
Tuesday, 11 March 2008
Crossing the highway
Last week we had in Madrid the first meeting of the “Board for the follow-up of GRID Spain activities”. I think this is the first time such board has been created to follow the progress of the projects funded by the Particle Physics program of the Spanish Ministry of Education. The classic yearly written report has been upgraded to a meeting with oral presentations and an evaluation board.
The meeting started with three presentations, one for each of the experiments, aiming to report on the state of the LCG from the point of view of each of them. It was quite interesting to see how the three talks were presenting completely different views about the same issue.
Both ATLAS and CMS mentioned the need of some sort of Tier-3s for the users to make their final analysis. There was some general concern due to the fact that such infrastructures are currently not being funded. The LHCb presentation was, from my point of view, the one that most directly presented the "view from the LCG users". The small number of physicists actually using the Grid was mentioned, and the most common problems found by them described. There was the usual "30% of the jobs sent to the Grid fail", and "sometimes the sites do not work, sometimes the experiment framework does not work". The result is always the same: the user just leaves saying "the Grid does not work". After some years of working trying to make "a Grid site to work" I really do think now that many of the problems remaining today are due to the experiment frameworks not working, or not properly managing the complexity of the Grid.
I presented the status of the Tier-1 at PIC, focusing in the last results obtained in the recent test CCRC08. Most of the results were actually quite positive, so I am quite confident that the board got the message "ther Tier-1 at PIC is working". It was also quite helpful to see direct references to the good performance of PIC in some of the Tier-2s presentations, like the LHCb one (thanks Ricardo).
There were two points I would like to highlight from the PIC presentation. The first one arose when showing two plots where the actual cost of equipment was compared to two CERN estimations: the one used in the proposal (oct-2006), and the update received three months ago. The results suggest that the hardware cost is lower than the estimation in the proposal. I think there are plenty of moving parameters in this project, one is the hardware cost estimations, but we should not forget that the event size, the cpu time or memory needed to generate a MonteCarlo event, the overall experiment requirements, etc. are also parameters with uncertainties of the order of 30 to 100%. If eventually we get to 2010 and the computing market has been such that prices have decreased faster than expected, good news. We will report this (as we already did with the past project and the delay of the LHC) and will propose to use the "saved" money for the 2011 purchases.
The second issue arose from a question from Les Robertson, who was a member of the board: "when do you expect that PIC will run out of power?". As the cpu and storage power of the equipment is (luckily for us!) exponentially growing, the power consumption of these wonderful machines is also going up to the sky. Soon the total input power at PIC will be raised from 200 KVA to 300 KVA. Though it is not an easy estimation, we believe this should be enough for the current phase of the Tier-1, up to 2010. Beyond that date, we should most probably be thinking about a major upgrade of the PIC site. Next to the UAB campus, on the other side of the highway, a peculiar machine is being built: a Synchrotron Ring. This stuff comes normally with a BIG plug... should we try and cross the highway to get closer to it?
The meeting started with three presentations, one for each of the experiments, aiming to report on the state of the LCG from the point of view of each of them. It was quite interesting to see how the three talks were presenting completely different views about the same issue.
Both ATLAS and CMS mentioned the need of some sort of Tier-3s for the users to make their final analysis. There was some general concern due to the fact that such infrastructures are currently not being funded. The LHCb presentation was, from my point of view, the one that most directly presented the "view from the LCG users". The small number of physicists actually using the Grid was mentioned, and the most common problems found by them described. There was the usual "30% of the jobs sent to the Grid fail", and "sometimes the sites do not work, sometimes the experiment framework does not work". The result is always the same: the user just leaves saying "the Grid does not work". After some years of working trying to make "a Grid site to work" I really do think now that many of the problems remaining today are due to the experiment frameworks not working, or not properly managing the complexity of the Grid.
I presented the status of the Tier-1 at PIC, focusing in the last results obtained in the recent test CCRC08. Most of the results were actually quite positive, so I am quite confident that the board got the message "ther Tier-1 at PIC is working". It was also quite helpful to see direct references to the good performance of PIC in some of the Tier-2s presentations, like the LHCb one (thanks Ricardo).
There were two points I would like to highlight from the PIC presentation. The first one arose when showing two plots where the actual cost of equipment was compared to two CERN estimations: the one used in the proposal (oct-2006), and the update received three months ago. The results suggest that the hardware cost is lower than the estimation in the proposal. I think there are plenty of moving parameters in this project, one is the hardware cost estimations, but we should not forget that the event size, the cpu time or memory needed to generate a MonteCarlo event, the overall experiment requirements, etc. are also parameters with uncertainties of the order of 30 to 100%. If eventually we get to 2010 and the computing market has been such that prices have decreased faster than expected, good news. We will report this (as we already did with the past project and the delay of the LHC) and will propose to use the "saved" money for the 2011 purchases.
The second issue arose from a question from Les Robertson, who was a member of the board: "when do you expect that PIC will run out of power?". As the cpu and storage power of the equipment is (luckily for us!) exponentially growing, the power consumption of these wonderful machines is also going up to the sky. Soon the total input power at PIC will be raised from 200 KVA to 300 KVA. Though it is not an easy estimation, we believe this should be enough for the current phase of the Tier-1, up to 2010. Beyond that date, we should most probably be thinking about a major upgrade of the PIC site. Next to the UAB campus, on the other side of the highway, a peculiar machine is being built: a Synchrotron Ring. This stuff comes normally with a BIG plug... should we try and cross the highway to get closer to it?